Construction of KKH Phase-II Havelian-Thakot (118.057 KM) Part of CPEC

Brief Scope / Objectives of the Project
Construction of 120.12 km long Havelian–Thakot expressway. 4 lanes from Havelian to Mansehra (39 km) and 2 lane facility from Mansehra to Thakot (81.12 km).

Benefits of the Project
The project will significantly enhance the potential for increased international trade between China and Pakistan and also with the Central Asian Republics.


Approved Cost: Rs.136659.66 Million

Final Expenditure: Rs.118137.67 Million

Expenditure During FY 2019-20: Rs.31472.51 Million

Date of Commencement: September, 2016

Date of Completion: June, 2020

Operationalized (Yes/No), if no reasons: Partly operationalized

Date of Inauguration (if inaugurated): 18th Nov, 2019 Havelian-Mansehra Section

Physical Progress (%)


a) Overall

100%

b) During FY 2019-20

NILL


Remarks
Havalian-Mansehra 39 km section is operational since Nov, 2019. Mansehra-Thakot section is likely to be opened for traffic soon.

PSDP S# 59